Frequently asked questions about the procedures preceding the installation of a pergola or carpot. Whether one is in an apartment building, a private home or a business, regulations change. The necessary permits and authorizations that allow the desired project to be put in place may differ from the destination. For any information not on the FAQ page, please contact our toll-free number 800.984.668
(Also with photovoltaics)
Construction of New Canopy in a detached and isolated position from the existing building.
All applicable regulations on distances even within the property must be complied with. Some municipalities may be required to maintain the 10-meter distance from the dwelling building as well. The civil code where not specified by local regulations would impose the distance of 3 m.
ONLY IN LANDSCAPE CONSTRAINT AREA
Prior Landscape Authorization (90 to 120 days after application) to be obtained from the competent Superintendence.
IN ALL CASES
Building Permit to be applied for at the municipal technical offices (60 to 120 days).
Superintendence and municipality requests can be concurrent and made at the same time.
TAX DEDUCTIONS ARE NOT AVAILABLE
BECAUSE THE WORK CONSTITUTES NEW CONSTRUCTION
CONSTRUCTION PROJECT OF THE ENTIRE EXISTING BUILDING
(not just cadastral plan)
If not present, it is necessary to submit a request to the municipality to have the project
SURVEY OF THE PROPERTY TO VERIFY URBAN PLANNING REQUIREMENTS
AND CIVIL ISSUES.
In the case of commercial activities and for the construction of photovoltaic canopies, it is possible to apply to the municipality for a so-called “Exceptional Building Permit” through the Productive Activities Desk (SUAP).
In this way it is possible: to apply for and obtain the construction of photovoltaic canopies even in derogation of the provisions of municipal regulations.
What does it mean concretely?
That if certain requirements are not present or missing in the implementation zone, they can be surpassed by applying to the municipality for a special permit to build for the purpose of business activity.
(Also with photovoltaics)
Construction of New Canopy in location abutting the existing building.
The distance to other neighboring buildings remains to be verified.
The construction of a lean-to canopy can fit within a building renovation project. Depending on whether it is included in a renovation project or not, the relevant standards change.
ONLY IN LANDSCAPE CONSTRAINT AREA
Prior Landscape Authorization (90 to 120 days after application) to be obtained from the competent Superintendency
IN ALL CASES
Building permit to be applied for at the municipal technical offices (60 to 120 days)
In some municipalities SCIA in case of Renovation project (30 days after filing)
Superintendence and municipality requests can be concurrent and made in the
same time.
In this case the times do not add up but overlap (i.e. total 120gg)
TAX DEDUCTIONS ARE NOT AVAILABLE
BECAUSE THE WORK CONSTITUTES NEW CONSTRUCTION
In the case of inclusion in an existing building renovation project, it can be deducted at 50 percent subject to the overall expenditure ceiling of 96,000 euros.
The ceiling refers to all renovation works altogether without distinction and therefore also to the new canopy.
A renovation intrevention is when a set of renovation works are carried out on the property that transform the building.
It is sufficient, for example, to intervene on the building elevations (changedimension of the window hole) or on the interior (move walls or add walls to divide rooms). An extension of the existing building is not to be made.
ALTERNATIVELY.
IF WITH PHOTOVOLTAIC YOU CAN TRY THE 110% ECO-SUPERBONUS
Also as part of a building renovation (see above) that involves energy improvements to the building, it is possible to access the 110% Eco-Superbonus by reaching different thresholds and targets:
To activate the Superbonus for solar photovoltaic panels, one must do at least one driving work (coat or boiler of a particular type) and together provide for the installation of the photovoltaic system, all provided that there is a final increase after the intervention of at least two energy classes of the property.
IN THIS CASE BUT THE MAXIMUM AMOUNT ALLOWED FOR SPENDING IS €1600/kw of system + any €1000/Kw of storage.
CONSTRUCTION PROJECT OF THE ENTIRE EXISTING BUILDING
(not just cadastral plan)
If not present, it is necessary to submit a request to the municipality to have the project
SURVEY OF THE PROPERTY TO VERIFY URBAN AND CIVIL REQUIREMENTS
CONSTRUCTION PROJECT OF THE ENTIRE EXISTING BUILDING
(not just cadastral plan)
If not present, it is necessary to submit a request to the municipality to have the project
SURVEY OF THE PROPERTY TO VERIFY URBAN AND CIVIL REQUIREMENTS
(New arbor)
Construction of a fixed structure, WITHOUT A FIXED IMPERMEABLE COVER.
The pergola from an urban planning point of view is characterized by a structure designed to support a non-fixed roof. For this reason, unless otherwise stipulated in municipal regulations, a retractable awning is also allowed since it does not constitute a fixed cover.
The construction of a pergola, moreover, can fit within
A building renovation project.
Depending on its inclusion in a renovation project
or not change the reference standards.
ONLY IN LANDSCAPE CONSTRAINT AREA
Prior Landscape Authorization (45 to 60 days after application) to be obtained from the competent Superintendence.
IN ALL CASES
Notification of Commencement of Work to the Municipality signed by an engineer if only pergola.
(Start of work immediately following the filing of documentation)
SCIA in City Hall in case of Renovation project (30 days after filing)
Superintendence and municipality requests can be concurrent and made at the same time. In this case the times do not add up but overlap (i.e. total 60gg)
TAX DEDUCTIONS ARE NOT AVAILABLE
BECAUSE THE WORK CONSTITUTES NEW CONSTRUCTION
In the case of inclusion in an existing building renovation project, it can be deducted at 50 percent subject to the overall expenditure ceiling of 96,000 euros. The ceiling refers to all renovation works altogether without distinction and therefore also to the new canopy.
A renovation intrevention is when a set of renovation works that transform the building are carried out on the property.
It is enough, for example, to work on the building elevations (change window hole size) or the interior (move walls or add walls to divide rooms).
An extension of the existing building is not to be made.
CONSTRUCTION PROJECT OF THE ENTIRE EXISTING BUILDING
(not just cadastral plan) If not present, it is necessary to submit a request to the municipality to have the project
SURVEY OF THE PROPERTY TO VERIFY URBAN AND CIVIL REQUIREMENTS
Boundary distances of 1.5 meters (except less restrictive municipal regulations)
distance from neighboring buildings 3 meters (except less restrictive municipal regulations)
(New pergola with photovoltaics)
Construction of a fixed structure, WITHOUT A FIXED IMPERMEABLE COVER. The pergola from an urban planning point of view is characterized by a structure designed to support a permeable roof. In this framing, spaced photovoltaic panels can be adopted to cover the pergola.
Important to ensure permeability and thus not create a water impermeable cover surface in any way. The construction of a pergola, moreover, can fit within a building renovation project.
Depending on whether it is included in a renovation project or not, the relevant standards change.
ONLY IN LANDSCAPE CONSTRAINT AREA
Prior Landscape Authorization (45 to 60 days after application) to be obtained from the competent Superintendence.
IN ALL CASES
Notification of Commencement of Work to the Municipality signed by an engineer if only pergola.
(Start of work immediately following the filing of documentation)
SCIA in City Hall in case of Renovation project (30 days after filing)
Superintendence and municipality requests can be concurrent and made at the same time. In this case the times do not add up but overlap (i.e. total 60gg)
TAX DEDUCTIONS ARE NOT AVAILABLE
BECAUSE THE WORK CONSTITUTES NEW CONSTRUCTION
In the case of inclusion in a renovation project of the existing building, it can be deducted at 50 percent in compliance with the overall expenditure ceiling of 96,000 euros.
the ceiling is for all renovation work altogether without distinction, and therefore also for the new canopy.
A renovation intrevent is when a set of renovation works are carried out on the property that transform the building. It is enough, for example, to work on the building elevations (change window hole size) or the interior (move walls or add walls to divide rooms). An extension of the existing building is not to be made.
ALTERNATIVELY.
IF WITH PHOTOVOLTAIC YOU CAN TRY THE 110% ECO-SUPERBONUS
Also as part of a building renovation (see above) that involves energy improvements to the building, it is possible to access the110% Eco-Superbonus by reaching different thresholds and targets:
To activate the Superbonus for solar photovoltaic panels, one must do at least one driving work (coat or boiler of a particular type) and together provide for the installation of the photovoltaic system, all provided that there is a final increase after the intervention of at least two energy classes of the property. IN THIS CASE BUT THE MAXIMUM AMOUNT ALLOWED FOR SPENDING IS €1600/kw of system + any €1000/Kw of storage.
CONSTRUCTION PROJECT OF THE ENTIRE EXISTING BUILDING
(not just cadastral plan)
If not present, it is necessary to submit a request to the municipality to have the project
SURVEY OF THE PROPERTY TO VERIFY URBAN AND CIVIL REQUIREMENTS
NEW CANOPY CANTILEVERED FROM THE BUILDING
With sheet metal/roofing/non-permeable materials covering
– with and/or without photovoltaics
Construction of New Canopy cantilevered from the facade of the existing building.
The maximum overhang for not falling under the regulations of lean-to canopies (ref. Lean-to canopies above), is 1.5 meters. The 1.5-meter overhang does not require compliance with any special distances or verification of particular urban planning indices. There is no maximum extent in development along the facade.
For overhangs greater than 1.5 meters, the standards for lean-to canopies must be followed.
The construction of a cantilever roof is part of a project that falls under the ceteogory of Renovation.
ONLY IN LANDSCAPE CONSTRAINT AREA
Prior Landscape Authorization (45 to 60 days after application) to be obtained from the competent Superintendence.
IN ALL CASES
SCIA for Renovation project (30 days from filing)
Superintendence and municipality requests can be concurrent and made at the same time.
In this case the times do not add up but overlap (i.e. total 60gg)
IN THE CASE OF INCLUDING IN AN EXISTING BUILDING RENOVATION PROJECT, IT CAN BE DETRACTED AT 50% WITH RESPECT TO THE OVERALL EXPENSE MAXIMUM OF 96,000 euros. THE CEILING IS FOR ALL RENOVATION WORK ALTOGETHER WITHOUT DISTINCTION, AND THEREFORE ALSO FOR THE NEW CANOPY.
A renovation intrevent is when a set of renovation works are carried out on the property that transform the building. It is enough, for example, to work on the building elevations (change window hole size) or the interior (move walls or add walls to divide rooms).
An extension of the existing building is not to be made.
ALTERNATIVELY?
IF WITH PHOTOVOLTAIC YOU CAN TRY THE 110% ECO-SUPERBONUS
Also as part of a building renovation (see above) that involves energy improvements to the building, it is possible to access the 110% Eco-Superbonus by reaching different thresholds and targets:
To activate the Superbonus for solar photovoltaic panels, one must do at least one driving work (coat or boiler of a particular type) and together provide for the installation of the photovoltaic system, all provided that there is a final increase after the intervention of at least two energy classes of the property.
IN THIS CASE BUT THE MAXIMUM AMOUNT ALLOWED FOR SPENDING IS €1600/kw of system + €230/sqm of solar shading + any €1000/Kw of storage.
CONSTRUCTION PROJECT OF THE ENTIRE EXISTING BUILDING
(not just cadastral plan)
If not present, it is necessary to submit a request to the municipality to have the project
What requirements do you need to have in order to apply the Superbonus to Photovoltaics and Storage Systems?
YOU NEED TO PERFORM AT LEAST ONE OF THESE INTERVENTIONS TRAINERS:
INSTALLATION OF SOLAR PHOTOVOLTAIC SYSTEMS
1) connected to the power grid;
2) installed on buildings or appurtenant structures;
3) Obligation to connect to the grid and network.
In the case of new structures such as canopies, the intervention is a Renovation intervention.
Since this is a Renovation work, the Expenditure Limit is 1600 €/Kw.
The 110% rate applies to the portion of expenditure corresponding to the maximum power of 20 kW.
For the portion of the expenditure corresponding to the power exceeding 20 kW, a 50% deduction is due with an expenditure ceiling of 96000 Euro.
Intervention that can be combined with Photovoltaics.
There is an expenditure ceiling of 1,000 euros per kW of system storage capacity.
The information was reprocessed from information found on the institutional portals of
Revenue Agency and ENEA’s Energy Efficiency Unit Department.
For more information and insights, please refer to their respective institutional websites:
https://www.agenziaentrate.gov.it/portale/web/guest/schede/agevolazioni
– https://www.efficienzaenergetica.enea.it/